Construction of Crane Dance Structure, Reclamation and Installation Works in Cruise Bay
from Port Notice No. 135 of 2009 dated 30 Sep 09;
This is an extension of Port Marine Notice No. 39 of 2009. The working period and working details have been revised.
With effect from 1 Oct 2009 to 31 Mar 2010, 24 hours daily including Sundays and Public Holidays. In Cruise Bay, off Sentosa (see plan above):
The construction entails dredging, installation of fascia panels to the seawall and installation of cranes on the crane dance structure. The crane dance structure (Point 11), is sited within the current working area for the seawall and reclamation project. Crane barges and flat top barges will be used for transportation of steel pipe piles and pre-cast concrete elements. The barges used in the project works will be shifted by tugs operating in pusher mode. Safety boats will be in attendance throughout the duration of the operation. For enquiries, please contact the project manager, Mr Chris Kelly at Tel: 9118 2802 (email: Chris_Kelly@macdow.com.au).