Massive Jurong reclamation continues until Nov 10

Reclamation at Jurong Island continues. And MORE reclamation may be considered. Just after announcing that reclamation at Jurong Island was completed 20 years ahead of schedule, JTC says it is contemplating more reclamation as land has already run out on the Island. 75% of the island's land has already been taken up or reserved by investors.
Cyrene Reef: Right next to Jurong and Bukom
View of Jurong Island from the vast seagrass meadows of Cyrene Reef.

More details about how Jurong Island was developed and some plans for its future.

Reclamation of Jurong Island Phase 4
from Port Marine Notice No. 50 of 2010 dated 7 May 2010.

This is a revision of Port Marine Notice No. 188 of 2009 [probably should be 81 of 2009]. The working areas have been revised and the working period has been extended.

With effect from 12 May 2010 to 11 Nov 2010. 24 hours daily including Sundays and Public Holidays. Western part of Singapore (see attached plan).
The reclamation works will involve cutter suction (CS) dredgers, trailer-suctionhopper (TSH) dredgers and hopper barges. Shore protection works will be carried out by crane barges and the dredging of sand-key trench by grab dredger. Marine soil investigation works will be carried out by jack-up barge within Working Area “C”. Further enquiries relating to the project can be directed to Mr T. Watanabe, the project manager at Tel No: 9668 1523 (email: t.watanabe@mypenta.net).

Reclamation of Jurong Island Phase 4
from Port Marine Notice No. 140 of 2010 dated 1 Nov 10
This is a revision of Port Marine Notice No. 50 of 2010. The working period has been extended.

With effect from 12 Nov 2010 to 11 May 2011, 24 hours daily including Sundays and Public Holidays. At Western part of Singapore (see attached plan):

The reclamation works will involve cutter suction (CS) dredgers, trailer-uctionhopper
(TSH) dredgers and hopper barges. Shore protection works will be carried out by crane barges and the dredging of sand-key trench by grab dredger. Marine soil investigation works will be carried out by jack-up barge within the working Area “C”. Further enquiries relating to the project can be directed to Mr T. Watanabe, the
project manager at Tel No: 9668 1523 (email: t.watanabe@mypenta.net).