Activities include dredging and "shore protection works"


Reclamation of Jurong Island Phase 4
from Port Marine Notice No. 81 of 2009 dated 1 Jul 09.
This is a revision of Port Marine Notice No. 220 of 2008 (see below). The working period has been extended.

With effect from 3 Jul 2009 to 2 Jan 2010, 24 hours daily including Sundays and Public Holidays, Western part of Singapore (see attached chartlet):


The reclamation works will involve cutter suction (CS) dredgers, trailer-suctionhopper (TSH) dredgers and hopper barges. Shore protection works will be carried out by crane barges and the dredging of sand-key trench by grab dredger. Marine soil investigation works will be carried out by jack-up barge within Working Area “C”. Further enquiries relating to the project can be directed to Mr T. Watanabe, the construction manager at Tel No: 9668 1523 (email: t.watanabe@mypenta.net).


Reclamation of Jurong Island Phase 4
from Port Marine Notice No. 220 of 2008 dated 26 Dec 08
This is a revision of Port Marine Notice No. 120 of 2008. The working period has been extended.

With effect from 3 Jan 09 to 02 July 09, 24 hours daily including Sundays and Public Holidays. at the Western part of Singapore (see attached plan):

The reclamation works will involve cutter suction (CS) dredgers, trailer-suctionhopper (TSH) dredgers and hopper barges. Shore protection works will be carried out by crane barges and the dredging of sand-key trench by grab dredger. Marine soil investigation works will be carried out by jack-up barge within Working Area “C”. Further enquiries relating to the project can be directed to Mr T. Watanabe, the construction manager at Tel No: 9668 1523, email: t.watanabe@mypenta.net