Dredging works at Cruise Bay
from Port Marine Notice No. 111 of 2009 dated 14 Aug 09
With effect from 17 Aug 09 to 31 Aug 09. 24 hours daily including Sundays and Public Holidays. At Cruise Bay and its vicinity (see attached chartlet):
Dredging works will be carried out using a clam shell onboard the crane barge, held by 4-point anchor moorings. Dredged materials will be transported to the designated dumping ground. A minimum of two split hopper barges will be mobilized for the transport of the excavated material. For all barge movements 1 pusher and 1 tug will
assist in maneuvering. All anchor points will be marked by buoys with lights. Safety boat will be in attendance at all times to warn and re-direct craft in the vicinity to keep clear of the on-going dredging work area.
Further general enquiries relating to the project can be directed to Mr Chris Kelly, the project manager at Tel: 9118 2802(email: chris.kelly@macdow.com.sg).
Dredging works at Cruise Bay
from Port Marine Notice No. 120 of 2009 dated 27 Aug 09
This is a revision of Port Marine Notice No. 111 of 2009. The working period has been extended.
With effect from 27 Aug 09 to 15 Oct 09. 24 hours daily including Sundays and Public Holidays. At Cruise Bay and its vicinity.
Dredging works will be carried out using a clam shell onboard the crane barge, held by 4-point anchor moorings. Dredged materials will be transported to the designated dumping ground. A minimum of two split hopper barges will be mobilized for the transport of the excavated material. All anchor points will be marked by buoys with lights. Safety boat will be in attendance at all times to warn and re-direct craft in the vicinity to keep clear of the on-going dredging work area. Further general enquiries relating to the project can be directed to Mr Chris Kelly, the project manager at Tel: 9118 2802(email: chris.kelly@macdow.com.sg).