Demolition works next to Labrador's natural shore, Jun-Oct 2015

Demolition works will happen close to Labrador's natural shore in the next five months.
This is a photo of our last trip on this shore in Oct 2014. The jetty to be demolished is quite close to the shore we were exploring. During that trip, we observed that the seagrasses were doing quite well.


From Port Marine Notice NO. 072 OF 2015 dated 19 Jun 2015

DEMOLITION OF JETTY AT PASIR PANJANG POWER STATION

Date : With effect from 22 Jun 2015 to 22 Oct 2015.
Location : Off Pasir Panjang Power Station, within the working area bounded by the
following co-ordinates (see attached chartlet):
Working Hours : From 0800 hours to 1900 hours daily including Sundays and Public Holidays

The demolition work will be carried out by crane barge assisted by tug boats. Divers will also be deployed for underwater cutting work. A safety boat will be deployed in the vicinity of the working area to warn other craft and vessels of the work. Further enquires relating to the project can be directed to Mr Thomas Nie, Engineer, HSL Construction, at Tel: 9718-8935 (email: kaixiong@hsl.com.sg).

Demolition work is extended to Dec 2015

From PORT MARINE NOTICE NO. 126 OF 2015 dated 13 Oct 2015

DEMOLITION OF JETTY AT PASIR PANJANG POWER STATION

This is a revision of Port Marine Notice No. 72 of 2015. The working period has been extended.

With effect from 23 Oct 2015 to 22 Dec 2015. Off Pasir Panjang Power Station, within the working area bounded by the
following co-ordinates (see attached chartlet, above):

The demolition work will be carried out by crane barge assisted by tug boats. Divers will also be deployed for underwater cutting work. A safety boat will be deployed in the vicinity of the working area to warn other craft and vessels of the work. Further enquires relating to the project can be directed to Mr Thomas Nie, Engineer, HSL Construction, at Tel: 9718-8935 (email: kaixiong@hsl.com.sg).


REMOVAL OF JETTY AT PASIR PANJANG POWER STATION
From PORT MARINE NOTICE NO. 02 OF 2016 dated 04 Jan 2016

Date : With effect from 05 Jan 2016 to 05 Mar 2016.
Location : Off Pasir Panjang Power Station, within the working area bounded by the following co-ordinates (see attached chartlet):

From 0800 hours to 1900 hours daily including Sundays and Public Holidays.

The removal work will be carried out by crane barge assisted by tug boats. Divers will also be deployed for underwater cutting work. A safety boat will be deployed in the vicinity of the working area to warn other craft and vessels of the work. Further enquires relating to the project can be directed to Mr Thomas Nie, Engineer, HSL Construction, at Tel: 9718-8935 (email: kaixiong@hsl.com.sg).