14 January 2009

Repair to seawall opposite Changi Jetty

The existing wall will be removed and restored. Work will involve a barge.
Changi Coastal Boardwalk: Changi Jetty
The wall is opposite Changi Jetty, where we take the bumboats to visit Pulau Ubin.

Repair Works to Revetment Seawall at Changi Creek
From Port Marine Notice No. 06 dated 13 Jan 09
With effect from 19 Jan 09 to 02 Apr 09, 0800 to 1800 hours daily, including Sundays and Public Holidays at Changi Creek (see attached plan):


The works will entail the removal of the existing wall and restoring the wall with armour rocks. A safety boat will be deployed to warn other craft to keep clear of the barge for the whole duration of the works. Further enquiries relating to the project can be directed to Mr. Bobby Woon, the project director, at Tel: 9456 6876 (email: bobby@thong-huat.com.sg).

LinkWithin

Related Posts with Thumbnails