Shore construction at Sungei Punggol continues until May 09

Installation of a temporary cofferdam; and construction of gate house, spillway and dam began in May 08 and will continue to May 09. The work area is opposite western Pulau Ubin.

Dredging and Marine Construction Works at Sungei Serangoon
Port Marine Notice No. 202 of 2008 dated 20 Nov 08
This is a revision of Port Marine Notice No. 107 of 2008. The working period has been extended.

With effect from 26 Nov 08 to 25 May 09, at Sungei Serangoon, (see attached plan):
Dredging works will be carried out by grab dredgers. The grab dredgers will be held by 4-point anchoring system and each anchor position will be marked by a yellow buoy, Fl Y 3s.

Installation of temporary cofferdam; and construction of gate house, spillway and dam will be carried out within the working area. Further enquiries relating to the project can be directed to Mr Mok Chin Ket, the project director, at Tel. 9628 7370, email: mokck@koon.com.sg.